Dunwoody City Council takes up a $186,000 design contract for the Ashford Dunwoody Road path Monday, and new bid conditions for city land near Georgetown Park.

The Dunwoody City Council is set to discuss a $186,000 contract for final construction plans for the next phase of the Ashford Dunwoody Road path at 6 p.m. Monday, Nov. 30, at City Hall. The phase runs from Perimeter Center West north toward Meadow Lane Road, according to the council’s Nov. 30 agenda. The next day, the city’s Urban Redevelopment Agency takes up new bid conditions for redeveloping its land near Georgetown Park.

Ashford Dunwoody Road path, phase 2

The contract is with Practical Design Partners, LLC, for $186,000 in design updates and final construction plans, plus $12,000 for design contingencies, the staff memo said. The fee would come from the project budget in the Hotel/Motel Tax fund.

  • The city has spent two years buying right of way between Perimeter Center West and Meadow Lane Road. The memo puts that at about 50% complete.
  • The city signed an agreement with the Perimeter Center Improvement District in November 2024 to buy the right of way and build that stretch.
  • The Perimeter Village shopping center at 4721 Ashford Dunwoody Road is redeveloping part of its site. As a condition of its development permit, the property owner will dedicate the right of way and build part of the slope work along its frontage. The memo said that lets the city carry the first segment to the Ashford and Ashwood Parkway intersection.
  • Staff split phase 2 into three segments: Perimeter Center West to Ashwood Parkway, then to Ashford Center Parkway, then to Mount Vernon Road. Once the first segment’s land is bought, the city will work with the improvement district on money for the second, which links to Dunwoody Village.
  • The design presentation shows a two-way cycle track on the west side from Perimeter Center West to Perimeter Center North, then one-way cycle tracks on both sides up to Ashford Center Parkway.

The item is listed for discussion on Monday’s agenda.

Also on the agenda

  • Urban Redevelopment Agency property, Georgetown. The agency meets at 5 p.m. Tuesday, Dec. 1, to consider updated conditions for its invitation to bid. The winning bidder would have to seek a rezoning from commercial to residential or mixed residential and live-work use. Homes on the east side of Georgetown Park should be detached single-family houses. The plan must include a public linear park linking Georgetown Park to Dunwoody Park and North Shallowford Road, plus a parklet near that intersection, both given to the city. The Georgetown plan the council approved in October also covered the agency’s land at North Shallowford Road and Dunwoody Park. The agenda.
  • On-call engineering firms. The council will discuss one-year contracts with a pool of firms for road, intersection, bike and pedestrian, traffic signal, stormwater, landscape, survey and right-of-way work. The city received 28 proposals in seven categories. The contracts can renew each year for up to three years, and larger task orders come back to the council. City Council, Monday, Nov. 30.
  • Connecting Dunwoody placemaking plan. The council will hear an update on the plan Monday.

What it means for you

  • City Council: 6 p.m. Monday, Nov. 30, in Dunwoody Hall at City Hall, 4800 Ashford Dunwoody Road. The agenda gives a Zoom link, dunwoodyga-gov.zoom.us/j/83080467641, and a call-in number, 470-381-2552, webinar ID 830 8046 7641. Public comment runs three minutes per speaker at the start and end of the meeting.
  • Urban Redevelopment Agency: 5 p.m. Tuesday, Dec. 1, in the City Manager’s Conference Room at City Hall, with three minutes per speaker for public comment.
  • Every city agenda, packet and summary is on the city’s Agenda Online portal.